445 Calendar

Hello Friends,

How do I create 445 calendar months with Sunday as the start date and the last Saturday as the month's end.

I did create this script, Buts weeks are not falling in to correct month, for example, Jan is ending on 02/23  supposed to be end on 01/28 according to 445

Set vCal_FD = 6;
Set vCal_RD = 7;

Date( WeekStart( $(CancelDateOO), 1, $(vCal_FD) ) - $(vCal_RD) ) as week startdate,
Num(Month(floor( WeekStart( $(CancelDateOO), 1, $(vCal_FD) ) - $(vCal_RD) ))) as MonthNum,

202301

01/01/23

01/28/23

202302

01/29/23

02/25/23

202303

02/26/23

04/01/23

202304

04/02/23

04/29/23

202305

04/30/23

05/27/23

202306

05/28/23

07/01/23

202307

07/02/23

07/29/23

202308

07/30/23

08/26/23

202309

08/27/23

09/30/23

202310

10/01/23

10/28/23

202311

10/29/23

11/25/23

202312

11/26/23

12/30/23

Labels (3)
1 Reply
Bill_Britt
Former Employee
Former Employee

Hi,

 

Take a look at this.

https://community.qlik.com/t5/Design/Recipe-for-a-4-4-5-Calendar/ba-p/1464069