Given Data Table:
Date | Month | Amt |
1/1/2012 | Jan | 100 |
2/1/2012 | Jan | 200 |
15/1/2012 | Jan | 500 |
31/1/2012 | Jan | 800 |
1/2/2012 | Feb | 600 |
5/2/2012 | Feb | 300 |
10/2/2012 | Feb | 100 |
28/2/2012 | Feb | 150 |
1/3/2012 | Mar | 200 |
5/3/2012 | Mar | 400 |
15/3/2012 | Mar | 600 |
31/3/2012 | Mar | 800 |
1/4/2012 | Apr | 100 |
5/4/2012 | Apr | 300 |
20/4/2012 | Apr | 500 |
30/4/2012 | Apr | 700 |
Required Scanario:
Apr | Mar | Feb | Jan |
Variance=400 | Variance=850 | Variance=450 | Variance=0 |
Sum=1600 | Sum=2000 | Sum=1150 | Sum=1600 |
700 | 800 | 150 | 800 |
500 | 600 | 100 | 500 |
300 | 400 | 300 | 200 |
100 | 200 | 600 | 100 |
Note: Please keep in mind that we will have to take date as a dimension
Please find attached data file as source
If you use Sum as your first Expression:
Expression1: =Sum(Amt)
Then for caculating Variance you may use:
Expression2: =After(Column(1))-Column(1)
If you use Sum as your first Expression:
Expression1: =Sum(Amt)
Then for caculating Variance you may use:
Expression2: =After(Column(1))-Column(1)